87% of govt projects are behind schedule
The Busega-Mpigi Expressway remains one of the most visible government projects that are behind schedule. Photo / File
What you need to know:
- Some of the stagnated projects include the Standard Gauge Railway, Kampala-Jinja Expressway, Busega-Mpigi Expressway, Entebbe Airport Rehabilitation Phase I, and Uganda Railways Corporation Capacity Building project
Nearly nine in every 10 government projects assessed by the Ministry of Finance are behind schedule, highlighting persistent problems in procurement, land acquisition, financing and project preparation.
A new review by the ministry’s Budget Monitoring and Accountability Unit (BMAU) found that 87 percent of 107 public investment projects assessed in June 2026 were behind schedule, virtually unchanged from the previous review in December 2025.
At least 14 projects, representing 13 percent of those assessed, had stagnated altogether, while 81, or 75.7 percent, registered only slight improvement.
The projects reviewed cut across 13 government programmes under the Public Investment Plan (PIP). Of the 107 projects, 62 were externally financed while 45 were funded by the government of Uganda.
The findings point to persistent weaknesses in the implementation of public investments, even as government continues to commit significant resources and borrow externally to finance infrastructure and development programmes.
The situation was worse among domestically funded projects, with 94 percent behind schedule compared with 80 percent of externally financed projects.
“Overall, 14 (13 percent) projects had stagnated while 81 (75.7 percent) had a slight improvement,” the report says.
Major projects stagnate
Among the 14 projects classified as stagnated are some of Uganda’s major transport, energy, and climate investments
Among the 14 projects classified as stagnated are some of Uganda’s major transport, energy and climate investments.
They include the Standard Gauge Railway, Kampala-Jinja Expressway, Busega-Mpigi Expressway, Entebbe Airport Rehabilitation Phase I and the Uganda Railways Corporation Capacity Building project.
Others are the upgrading of Katine-Ochero Road, Masaka-Mbarara 400kV Transmission Line, Clean Energy Access project, GET Access Uganda Mini-Grid Systems, Mineral Regulation Infrastructure and Uganda Geothermal Resources Development Project Phase II.
Climate-related investments were also affected, including the Building Resilient Communities, Wetland Ecosystems and Associated Catchments project, Irrigation for Climate Resilience, and a project designed to strengthen the resilience of communities and fragile ecosystems in the Katonga and Mpologoma catchments.
Externally financed projects accounted for 71.4 percent of the stagnated projects, according to the report, with transport and infrastructure investments accounting for a significant share.
The Ministry of Finance warned that delays on externally funded projects carry additional costs because government can incur charges on committed loans even when implementation and disbursement remain slow.
“This has grave implications for payment of commission fees on non-performing loans,” the ministry said.
Why projects are falling behind
The review identifies delayed procurement, inadequate project preparation and poor planning among the biggest constraints to implementation.
In some cases, weak preparation has forced implementing agencies to rescope projects after implementation has already started, further delaying delivery and increasing financing pressures.
Land acquisition and delays in securing Right of Way remain another major obstacle, particularly for transport, energy and other infrastructure projects.
Other constraints include inadequate or delayed counterpart funding, weak contractor capacity, delayed payments and non-disbursement of external financing.
BMAU also identified weaknesses in the systems used to plan, finance and implement public investment projects, which it said were contributing to poor utilisation of available project funds.
The findings suggest that securing financing alone is not enough to guarantee delivery.