81.3% of externally funded projects are behind schedule 

The Mineral Development Programme stands out as the top performer, completing its sole project amid widespread delays across other externally funded initiatives. Photo / File 

What you need to know:

  • Development ambitions stall as most externally funded projects lag behind schedule, exposing systemic planning failures

Externally funded development projects continue to fall behind schedule, with accounting officers citing weaknesses in planning, allocation, and implementation frameworks for public investment projects as the leading causes of poor utilisation of funds.

Key among others, a Ministry of Finance report indicates, is the non-disbursement of external financing, which limits realisation of intended benefits.

A report released by the Ministry of Finance shows that only 11.9 percent of projects are performing well (either completed or on track), while 81.3 percent remain behind schedule, consistent with previous assessments.

The report indicates that the Mineral Development Programme performed best as the only completed project. 

The Digital Transformation Programme had one of two projects on track, while the Human Capital Development Programme recorded three completed projects out of 12 (25 percent).

The worst-affected programme was the Natural Resources, Environment, Climate Change, and Land and Water Management Programme, which had 10 delayed projects.

Of the 48 delayed projects, 14.6 percent were stagnated, an improvement from 18 percent, while 77 percent showed slight progress, up from 75 percent. 

The Integrated Transport Infrastructure Programme accounted for 42.9 percent of the stagnated projects, down from 60 percent previously.

The report identifies the main causes of delays as delayed procurement processes, land acquisition issues related to right of way, weak contract management, poor project planning and readiness, and inadequate counterpart funding.

Permanent Secretary to the Treasury, Ramathan Ggoobi, noted in the report some improvement, with more projects completed and previously stagnated ones gaining momentum.
 
He, however, cautioned accounting to implement solutions to identified bottlenecks and improve project performance as a basis for contract renewal.

The Agriculture Value Chain Development Programme operates in 40 districts and aims to improve household incomes, enhance food security, and strengthen climate resilience.

Its physical progress reached 78 percent in November 2025, up from 72 percent, although still below the expected 82 percent timeline.
 
Financial disbursement stood at Shs259.115b, representing 79.3 percent, which marked a 5.1 percent increase.

Key outputs include irrigation systems, animal disease control infrastructure, trade facilitation, and agricultural research and development.

The programme focuses on the Uganda Digital Acceleration Project and the National Backbone Infrastructure Phase V.

Physical progress reached 14 percent in November 2025, up from 12 percent. Disbursement totalled $66.32m, with 51 percent of the funds utilised, reflecting a gradual improvement in fund absorption.

To improve project performance, the report recommends fast-tracking procurement processes, prioritising funding for land acquisition, strengthening contract management, and increasing mobilisation of counterpart funds.